SEPT. 12 -- OCT. 10:
Ultrathin asphalt layer for all three eastbound lanes.
OCT. 11 -- NOV. 5: Ultrathin asphalt layer for eastbound ramps and acceleration
lanes.
MARCH 17-- APRIL 5, 2008: Ultrathin asphalt layer for all three westbound lanes.
APRIL 7 -- APRIL 24, 2008: Ultrathin asphalt layer for westbound ramps and
acceleration lanes.
WHEN THEY WILL WORK
NIGHTS: Lanes under repair will be closed from 8 p.m. until 6 a.m. weekdays and
until 8 a.m. Saturday and Sunday.
NINE WEEKENDS: Daytime work will force certain lanes to be closed from 8 p.m.
Friday until 6 a.m. Monday.
Scheduled work weekends are: April 20-23; April 27-30; May 4-7; May 18-21; June
1-4; June 8-11; June 15-18; June 22-25; June 29-July 2.
WHEN THEY WILL NOT WORK
No lanes will be closed between 6 a.m. and 8 p.m. Monday through Friday. Work
also will be stopped on holidays, in the winter and for some special events:
Memorial Day: No work 6 a.m. Friday, May 25, to 8 p.m. Tuesday, May 28.
Independence Day: No work 6 a.m. Tuesday, July 3, to 8 p.m. Friday, July 6.
Labor Day: No work 6 a.m. Friday, Aug. 31, to 8 p.m. Tuesday, Sept. 4.
Winter stoppage: No paving between Nov. 15 and March 15.
Special events: Work hours restricted for events expected to generate heavy
traffic. For football and basketball games at area universities, graduations and
the State Fair, no lanes in the prominent travel direction will be closed six
hours before the event and six hours afterward.