State to spell out environmental report for NC540 completion

WTVD logo
Monday, December 7, 2015
Wake County Commission wants Orange Route for 540 loop
Proposed routes for the completion of 540
vod

RALEIGH (WTVD) -- The first of three public meetings will be held Monday night to allow residents to weigh in on the "Complete 540" project - which has been in the works for more than 20 years.

The catalyst was a federal environmental report the state received earlier last month that spells out the potential costs of each of the 17 possible routes the new road could take.

CLICK HERE TO SEE THE PROPOSED ROUTES (.pdf)

The report doesn't make recommendations or eliminate routes. It does clear the way for the project to move forward.

At the meetings, the state is expected to spell out the federal report and its conclusions: the impact on streams, wetlands, flood planes, farmlands, historic sites, publicly owned land, and - of course - people.

It spells out how many homes, businesses, and parcels of land would have to be bulldozed to make way for the new road and quantifies the actual costs of each route, ranging from 2.2 to 2.6 billion dollars.

Some people from the North Carolina Department of Transportation, representatives from towns along the potential paths, engineers, and other officials are expected to be in attendance at the meetings:

Monday, Dec. 7, 2015

Barwell Road Elementary School

3925 Barwell Road, Raleigh

Public Meeting: 6 to 8 p.m. (no formal hearing on this date)

Tuesday, Dec. 8, 2015

Holly Springs High School Cafeteria

5329 Cass Holt Road

Public Meeting: 6 to 8 p.m. (no formal hearing on this date)

Wednesday, Dec. 9, 2015

Wake Tech Community College - Student Services Building, Room 213/214

9101 Fayetteville Road, Raleigh

Public Meeting: 4 to 6:30 p.m., Hearing: 7 p.m.

The public comment period started last month; all comments have to be submitted by January 8.

Best case, the schedule for the project looks like this:

  • End of comment period - January 8
  • State selects preferred alternative - March 2016
  • Final federal environmental report - Late-2016
  • Decision accepted - 2017
  • First contract (of 3) awarded - 2018
  • Construction begins:

CLICK HERE TO READ THE REPORT (.pdf)

And check http://www.ncdot.gov/complete540 for project updates.

Report a Typo